Reference is made to the Tender Notice that appeared in the Authority’s website and the MyGov pullout on The Star Newspaper dated 25th March 2025.
Interested Bidders are requested to note the following amendments for the Tenders published under the above referenced Tender Notice;
S/N | CLARIFICATION SOUGHT | RESPONSE |
1 | RWC 682
Item 4.01-Rate for this Bill Item is already given in the document. Item 4.02-Rate for this Bill Item is already given in the document
Kindly clarify if we should adopt the given rates or the contractor is supposed to quote his own rates.
|
The BOQ’s for tender no’s RWC 682, RWC 683 and 684 have been revised including other corrections and the revised tender documents have been uploaded on the Authority’s website www.kerra.go,ke
|
2 | RWC-683-
1. Item 1.07-vehicle month is stated as 1, is it correct? 2. Item 7.04-stone pitching 77,000m3, is it too hogh? 3. Item 17.02- concrete class 25(20) is 1400m3, is this quantity correct or too high? 4. Item 17.11-steel reinforcement levy 0.03% is missing. 5. Summary page, procurement levy is missing. 6. Land compensation kshs 50,000,000 is it correct?
|
|
3 | RWC-684-
Item no.4.3the amount in the description is 1 million but the rate is indicated as 2,000,000 and sum is also indicated as 2,000,000.00 |