UPGRADING WORKS, REHABILITATION, SPOT IMPROVEMENT, GRAVELLING AND CONSTRUCTION OF STRUCTURES FOR THE FY 2025/2026-ADDENDUM 1

November 3, 2025 - In Tender Notice

KENYA RURAL ROADS AUTHORITY

                                                                          TENDER NOTICE

                                                                                                                                                                                                  

ADDENDUM NO. 1

UPGRADING WORKS, REHABILITATION, SPOT IMPROVEMENT, GRAVELLING AND CONSTRUCTION OF STRUCTURES FOR THE FY 2025/2026

Addendum No. 1 –3-11-2025

Reference is made to the Tender Notice that appeared in the Star Newspaper dated 2nd October, 2025, the Long Advert dated 21st October, 2025 and Clarification No. 1 dated 28th October, 2025.

Interested Bidders are requested to note the following amendments to the Tender Notice as follows;

 

  1. The Tender Documents Uploading Date for Lot 2 and Lot 3 tenders is hereby revised to 7th November, 2025.
  2. The Pre-Tender Site Visit Dates for Lot 2 tenders have been revised as detailed in Annex 1 attached The Pre-Tender Site Visit Dates for Lot 3 and Lot 4 remain unchanged. Interested Bidders should note that the assembly time for Pre-Tender Site Visit is 10.00 am at the Respective Regional Offices as detailed in the Long Advert.
  3. The Submission and Opening Date for Lot 2 tenders is hereby revised from 20th November, 2025 to on or before 28th November, 2025 at 11.00am.
  4. The Submission and Opening Date for Lot 1, Lot 3 and Lot 4 remains unchanged. Interested Bidders should note that the closing time shall be at 11.00am for all the tenders.
  5. The Location for the Tender for Kabucho – Kipkoris, Tender No. RWC 808 under Lot 3 is Nakuru and NOT Elgeyo Marakwet as given in the Long Advertisement.
  6. The Tender for Sebit – Parua – Tapach, Tender No. RWC/806 under Lot 3 is hereby CANCELLED.
  7. All interested bidders are required to continually check the Authority’s website: www.kerra.go.ke for any Tender Addendums or Clarifications that may arise before submission date.
  8. Bidders with enquiries are encouraged to do so vide the email address procurementhq@kerra.go.ke.
  9. All other information as pertaining to the tenders remains the same.

Deputy Director (Supply Chain Management)

For: DIRECTOR GENERAL

 

ANNEX 1

S/N Region Tender No Proposed Project Name Date of Uploading Tender Documents Date of Pretender Site Visit Date of Closing and Opening
Lot 2
1 Makueni RWC 730 E476b – Ukia- Kyuasini – Kyambeke Road 7th November, 2025 10th November, 2025 28th November, 2025
2 Meru RWC 731 Tutua – Mbaaria – Kirachene – Gitimene – Kiirua – Gitoro: Phase Kiirua – Gitoro 7th November, 2025 10th November, 2025 28th November, 2025
3 Migori RWC 732 Nyarobiro – Kombe – Masaba – Nyanchabo – Getong’anya – Ikerege-Tarang’anya Road Phase 1 7th November, 2025 10th November, 2025 28th November, 2025
4 Murang`a RWC 733 Kandara – Karima Mwaro – Gituya, Nguthuru – Gatitu – Karima Mwaro & Kibereke – Naaro – Kaburugi – Gatitu Roads 7th November, 2025 10th November, 2025 28th November, 2025
5 Nakuru RWC 734 Maji Punda – Itare Road 7th November, 2025 10th November, 2025 28th November, 2025
6 Narok RWC 735 Enengetia – Olpusimorru Road 7th November, 2025 10th November, 2025 28th November, 2025
7 Narok RWC 736 Enaramatishoriki Bridge 7th November, 2025 10th November, 2025 28th November, 2025
8 Narok RWC 737 Suswa – Inkorionito – Nairake – Enkare Road 7th November, 2025 10th November, 2025 28th November, 2025
9 Tharaka Nithi RWC 738 Kirege – Forest – Mabukuro 7th November, 2025 11th November, 2025 28th November, 2025
10 Tharaka Nithi RWC 739 Kibugua – Magenka – Itugururu 7th November, 2025 11th November, 2025 28th November, 2025
11 Uasin Gishu RWC 741 Kaptebengwet – Emkwen Estate 7th November, 2025 11th November, 2025 28th November, 2025
12 Uasin Gishu RWC 742 Nyalilbei – Ngeny – Lower Moiben – Segero and Loop Roads 7th November, 2025 11th November, 2025 28th November, 2025
13 Uasin Gishu RWC 743 Ziwa – Kimurgoi – Lomoiywet – Matunda 7th November, 2025 11th November, 2025 28th November, 2025
14 Uasin Gishu RWC 744 Kapsang – Kabobo – Cheplelaibei – Kapsumbeiywet – Fafarol 7th November, 2025 11th November, 2025 28th November, 2025
15 Uasin Gishu RWC 745 Turbo – Kaiboi – Kimondi – Chepterit Road (B123) 7th November, 2025 11th November, 2025 28th November, 2025
16 Uasin Gishu RWC 746 Selia – Turbo 7th November, 2025 11th November, 2025 28th November, 2025
17 Meru RWC 747 Phase 2 Maraa – Mworoga -Mitunguu 7th November, 2025 11th November, 2025 28th November, 2025
18 Embu RWC 748 Rianjeru – Rwika – Gachuriri – Kiritiri 7th November, 2025 11th November, 2025 28th November, 2025
19 Murang`a RWC 749 Gatura – Ngere – Karangi 7th November, 2025 11th November, 2025 28th November, 2025
20 Siaya RWC 750 Kodiaga – Rabango – Ratuoro – Usenge Road 7th November, 2025 11th November, 2025 28th November, 2025
21 Siaya RWC 751 Boro – Hawinga – Uwaasi Road 7th November, 2025 12th November, 2025 28th November, 2025
22 Siaya RWC 752 Sidindi – Sigomre – Masiro 7th November, 2025 12th November, 2025 28th November, 2025
23 Siaya RWC 753 Koyucho Junc – Uloma – Upanda 7th November, 2025 12th November, 2025 28th November, 2025
24 Siaya RWC 754 Ngiya – Kobare – Malele 7th November, 2025 12th November, 2025 28th November, 2025
25 Kericho RWC 755 Seretut Junction – Tti – Chepkutbei – Kapsoit – Kapnandet – Kotab Chago 7th November, 2025 12th November, 2025 28th November, 2025
26 Uasin Gishu RWC 756 Jabali – Saos 7th November, 2025 12th November, 2025 28th November, 2025
27 Migori RWC 757 Posta – Nyikendo – Nyarongi – Macalder 7th November, 2025 12th November, 2025 28th November, 2025
28 Machakos RWC 758 C439 Matuu – Ikombe – Katangi 7th November, 2025 12th November, 2025 28th November, 2025
29 Elgeyo Marakwet RWC 759 Chepkorio Township – Kaplimo – Kisaina Road 7th November, 2025 12th November, 2025 28th November, 2025
30 Trans Nzoia RWC 760 Kisawi Centre – Pango – Gituamba – Sosio Forest Station – Labot 7th November, 2025 12th November, 2025 28th November, 2025
31 Baringo RWC 761 Poror – Sirwo – Sorok – Ochii Road 7th November, 2025 12th November, 2025 28th November, 2025
40 Uasin Gishu RWC 762 Belekenya – Karlel – Kaptildil – Chepterit Road 7th November, 2025 12th November, 2025 28th November, 2025
41 Nandi RWC 763 Yala – Kobujoi – Potopoto 7th November, 2025 13th November, 2025 28th November, 2025
42 Bomet RWC 764 Kaptambuliet Bridge 7th November, 2025 13th November, 2025 28th November, 2025
43 Siaya RWC 765 Bondo Bypass 7th November, 2025 13th November, 2025 28th November, 2025
44 Kericho RWC 766 Panda Pilis – Kampala – Bakoyot – Mabasi Road 7th November, 2025 13th November, 2025 28th November, 2025
45 Migori RWC 767 Kanyawanga – Dede – Rapogi 7th November, 2025 13th November, 2025 28th November, 2025
46 Nandi RWC 768 Mugundoi – Nandi Hills-Kosiage – Cheptulu Roads 7th November, 2025 13th November, 2025 28th November, 2025
47 Trans Nzoia RWC 769 Kiminini – Solana – Kangoti 7th November, 2025 13th November, 2025 28th November, 2025
48 Migori RWC 770 Stella – Gogo 7th November, 2025 13th November, 2025 28th November, 2025
49 Migori RWC 771 Kabau – Bondo – Piny Oyie 7th November, 2025 13th November, 2025 28th November, 2025
50 Migori RWC 772 Otho – Got – Kachola 7th November, 2025 13th November, 2025 28th November, 2025
51 Homa Bay RWC 773 Koguta – Nyabera 7th November, 2025 13th November, 2025 28th November, 2025
52 Homa Bay RWC 774 Lwanda – Kanyakiano 7th November, 2025 14th November, 2025 28th November, 2025
53 Homa Bay RWC 775 Tonga – Kisaku – Osiri 7th November, 2025 14th November, 2025 28th November, 2025
54 Homa Bay RWC 776 Kalamindi – Osani – Nyakweri 7th November, 2025 14th November, 2025 28th November, 2025
56 Homa Bay RWC 777 Got Kojowi – Osogo – Otati 7th November, 2025 14th November, 2025 28th November, 2025
57 Kajiado RWC 779 Ngong Kibiku – Kangiria 7th November, 2025 14th November, 2025 28th November, 2025
LOT 3
1 Nakuru RWC 781 Elburgon Kasarani Link Roads 7th November, 2025 10th November, 2025 25th November, 2025
2 Uasin Gishu RWC 782 Kuinet – Kapchan – Tebeswet – Tebeson – Stabex 7th November, 2025 10th November, 2025 25th November, 2025
3 Bomet RWC 783 Kisyet Tea Factory – Kipyosit Secondary – Saparet – Kiptogoch – Kiromwok – Kapkesiego – Chepkongony – Njerian – Kapsimbiri – Kyogong Road Project; Phase 1 7th November, 2025 10th November, 2025 25th November, 2025
4 Bomet RWC 784 Daraja Sita – Chebirbelek – Kipanjala – Masset – Kapkoros 7th November, 2025 10th November, 2025 25th November, 2025
5 Nakuru RWC 785 Road C577, Kwa Gitau – Mogotio Road 7th November, 2025 10th November, 2025 25th November, 2025
6 Kericho/Uasin Gishu RWC 786 Ainamoi Centre – Kapsaos Road 7th November, 2025 10th November, 2025 25th November, 2025
7 Kericho RWC 787 Tegat– Kaplelit – Burutu – Kokwet Road/Toroton – Yalla – Chepkechei – Songenyet Road 7th November, 2025 11th November, 2025 25th November, 2025
8 Homa Bay RWC 788 Rangwe – Ndiru 7th November, 2025 11th November, 2025 25th November, 2025
9 Uasin Gishu RWC 789 Koisagat – Kapchemakilot – Sach – Kabenes 7th November, 2025 11th November, 2025 25th November, 2025
10 Kiambu RWC 791 Gacharage – Kagongo- St. Angela Secondary School Road 7th November, 2025 11th November, 2025 25th November, 2025
11 Kirinyaga RWC 793 Kwa Jesee – Nguguini 7th November, 2025 11th November, 2025 25th November, 2025
12 Uasin Gishu RWC 794 Kapseret – Saina Estate-Lobo 7th November, 2025 12th November, 2025 25th November, 2025
13 Uasin Gishu RWC 795 Royalton – Eldoret Southern Bybass 7th November, 2025 12th November, 2025 25th November, 2025
14 Elgeyo Marakwet RWC 796 Tachasis Chebiemit 7th November, 2025 12th November, 2025 25th November, 2025
15 Bungoma RWC 797 Mufupi – Mukuyuni – Naitiri Road 7th November, 2025 12th November, 2025 25th November, 2025
16 Uasin Gishu RWC 798 Kaiboi – Chepkober 7th November, 2025 12th November, 2025 25th November, 2025
17 Narok RWC 799 Mogondo – Charamgoi – Mogor – Soit Road 7th November, 2025 12th November, 2025 25th November, 2025
18 Bomet RWC 800 Kapkwen – Olbutyo – Siongiroi 7th November, 2025 12th November, 2025 25th November, 2025
19 Uasin Gishu RWC 801 Kaplelach – Cheparus – Jerusalem Road 7th November, 2025 12th November, 2025 25th November, 2025
20 Uasin Gishu RWC 802 Ngeria Primary – Moi University – Kapkoi Road 7th November, 2025 12th November, 2025 25th November, 2025
21 Kajiado RWC 803 Arankai – Rongai – Kalulo – Mataru 7th November, 2025 13th November, 2025 25th November, 2025
22 West Pokot RWC 804 Chesta – Sintai – Kapatet 7th November, 2025 13th November, 2025 25th November, 2025
23 West Pokot RWC 805 Ngotut – Kasei 7th November, 2025 13th November, 2025 25th November, 2025
24 West Pokot RWC 806 Sebit – Parua – Tapach (CANCELLED) 7th November, 2025 13th November, 2025 25th November, 2025
25 West Pokot RWC 807 Kirita Junction – Kanyarkwat 7th November, 2025 13th November, 2025 25th November, 2025
26 Nakuru RWC 808 Kabucho – Kipkoris 7th November, 2025 13th November, 2025 25th November, 2025
27 Nakuru RWC 809 Chebara – Wechego Road 7th November, 2025 14th November, 2025 25th November, 2025
28 Transzoia RWC 810 B234 – Kiminini Market-Mitoto – Ndalu- Brigadier Road 7th November, 2025 14th November, 2025 25th November, 2025
29 Kisumu RWC 811 Chiga – Rabuor 7th November, 2025 14th November, 2025 25th November, 2025
30 Kwale RWC 812 Kokotoni – Mavirivirini Primary – Kalalani Ecd 7th November, 2025 14th November, 2025 25th November, 2025
31 Kajiado RWC 813 Maparasha Bridge 7th November, 2025 14th November, 2025 25th November, 2025
32 Siaya RWC 814 Bondo – Uyawi 7th November, 2025 14th November, 2025 25th November, 2025
33 Kericho RWC 816 Furaha – Hill Tea 7th November, 2025 14th November, 2025 25th November, 2025
LOT 4
1 Kisii RWC 817 Etago – Ekona – Nyamaiya – Mogenda 12th November, 2025 17th November, 2025 27th November, 2025
2 Meru RWC 818 Kiengo – Ndambiro – Mangala – Mnp Road 12th November, 2025 17th November, 2025 27th November, 2025
3 Nyandarua RWC 819 Kwa Haraka – Rwanyambo – Karagatha – Kinamba 12th November, 2025 17th November, 2025 27th November, 2025
4 Kirinyaga RWC 821 Baricho – Njegas – Ngaru – Gakoigo – Kangaita -Kiaritha – Kerugoya 12th November, 2025 18th November, 2025 27th November, 2025
5 Trans Nzoia RWC 822 Cherangani – Kipkeikei – Suwerwa – Kmaoi – Kapcherop – Makuatno – Kaptalamwa 12th November, 2025 18th November, 2025 27th November, 2025
6 Homabay RWC 823 Suba South: Lak – Kogelo, Usengere – Onyuera, Kijito – Mwirari 12th November, 2025 18th November, 2025 27th November, 2025
7 Bungoma RWC 826 Kimilili – Kapsokwony 12th November, 2025 18th November, 2025 27th November, 2025
8 Mombasa RWC 827 Jaribuni – Dzitzoni Road 12th November, 2025 18th November, 2025 27th November, 2025
9 Meru RWC 828 Kaelo – Mulika – Antobetwe Kiongo – Ngaya – Kinanduba to Kiina Jnt Road 12th November, 2025 18th November, 2025 27th November, 2025
10 Kericho RWC 832 Kapsorok – Sondu – Kipkok – Mindililwet – Koilsir (Phase I) 12th November, 2025 19th November, 2025 27th November, 2025
11 Meru RWC 833 Kionyo – Kanyakine- Kithino 12th November, 2025 19th November, 2025 27th November, 2025
12 Nandi RWC 834 Kipcheken – Kapkemich Road 12th November, 2025 19th November, 2025 27th November, 2025
13 Kiambu RWC 835 Mount Kenya Mwiki Bridge – Kwangethe Primary School Road – Mwihoko Primary 12th November, 2025 20th November, 2025 27th November, 2025
14 Uasin Gishu RWC 838 Selia – Turbo 12th November, 2025 20th November, 2025 27th November, 2025
15 Elgeyo Marakwet RWC 839 St. Michael Kakimiti – Chawis Primary – Chepkoit Jnct – Kamogo – Lemeiywo Primary 12th November, 2025 20th November, 2025 27th November, 2025
16 Tharaka RWC 829 Turimatweru – Nkondi – Gatunga 12th November, 2025 21st November, 2025 27th November, 2025
17 Tharaka RWC 830 Murika – Ngage – Mukothima 12th November, 2025 21st November, 2025 27th November, 2025

Reach Us

Barabara Plaza Block B,

Airport South Road,

P.O Box 48151 – 00100
Nairobi, KENYA

Mon – Fri: 8:00 am – 5:00 pm

Our Newsletters

Subscribe to Receive our latest Newsletters

Connect With Us

Copyright © 2024 Kenya Rural Roads Authority . All Rights Reserved. || Developed by Xtranet Communication.